|
September 27, 2009
Arabtec has been awarded the first
tower contract for testing foundation works at the Okhta Centre in St
Petersburg, according to a senior official. It will sign two further
testing contracts by the year end, he added.
"These three contracts are
separate to the main contract for the project, which is still Dh10
billion," said Ziad Makhzoumi, CFO at Arabtec Holding, the Dubai-headquartered contracting company, yesterday in an interview.
It has signed the first Dh50
million contract for the testing of five deep foundation barrettes,
extending 70 metres into the soft ground, to establish their build
ability in the site subsoil and their bearing capacity to support the
main 400 metre high tower at the Okhta Centre development in St
Petersburg. The testing contract was awarded by Gazprom-Neft. Work has
already started on the project and is expected to be complete in five
months.
Arabtec is expecting to sign the next
contract by November for testing 10 piles with various diameters and
lengths. This second contract will be similar to the barrettes testing
contract and should be completed in six months.
"The value of the second
contract will be the same as the first," Makhzoumi told Emirates
Business. "The third contract will be bigger than the first two but I
will not disclose a value for the third contract in case Gazprom does
not approve it," he added. The third contract to be awarded by the end
of the year will be for testing of the diaphragm wall construction at
the site.
These series of tests are necessary to obtain the
building permit from planning authorities in St Petersburg before the
final project permit is issued. "When you submit, they have 60 days to
come back to you and we are trying to address all their concerns so
that we get the approval within the 60 days."
A statement from Arabtec yesterday said that the award of
this first contract and the expected further test contracts "confirms
the imminent intention of Gazprom-Neft to proceed with its plans to go
ahead with the construction of the Okhta Centre project subject to
final tests and designs being agreed and approved".
Makhzoumi
said in the current situation, "the government must change the zoning
of the area where the building will be constructed and this week saw
Gazprom-Neft winning final approval from the city of St Petersburg and
overcoming the previous objections to this project".
The main contract amount has been subject to "long and intense negotiations with Arabtec Construction for more than a year now", said the company in a statement. Arabtec Construction received the letter of award for
the above project in April 2008 and has since then been working closely
with Gazprom-Neft to develop method statements and budgets for the
project, it added.
"Once we start main construction by next
year, it will take four years to complete the project... say around
2014," Makhzoumi had told the newspaper in an earlier interview.
In
November 2005, Gazprom announced that Sibneft was going to build the
Gazprom City Business Centre and the British architectural firm RMJM
won the project in December 2006. In March 2007, the project was
renamed Okhta Centre (after the Okhta River).
The complex, on
the eastern edge of St Petersburg, will include a concert hall and
museum in addition to the skyscraper, which will house the headquarters
of Gazprom Neft, the oil arm of OAO Gazprom, the world's biggest
natural gas producer. When built, it may become Europe's tallest
skyscraper.
Source: Zawya
|